Archive for May, 2005

Delay Analysis – Bespoke



Richard Morris was appointed to provide programme advice and delay analysis in relation to a high-class residential development on behalf of the developer.



Adjudication Support – DOM/1



Morris Associates has been retained to provide advice to a contractor in relation to a DOM/1 mechanical and electrical services sub-contract where the sub-contractor has submitted a grossly inflated final account and loss and expense claim and was threatening to adjudicate and litigate, including issuing winding-up proceedings.